192 Bridge Work Update

Delays expected as utility lines are replaced.

192 Bridge Work Update
Foundations have been poured for the bridge over Toro Canyon Creek, one of six bridges destroyed by the January 9 debris flow.

Caltrans has revised the work and completion dates for the six bridges along State Route 192 that were damaged by the January 9 debris flow.

For the Arroyo Paredon Bridge, the pre-cast bridge deck should be lowered onto the abutments, whose foundations are being excavated now, by the end of September. Bridge completion is currently the end of November.

The bridges at Toro Canyon Creek and Romero Canyon Creek are on similar calendars. The foundations have been or are being poured, and the deck placements should begin next week. The reopening date for both is now the end of October.